Key System Update — Impact Map
Today is Tuesday, 12/08/2026
Pending
Work Program (via Work Program service)
Phase 52 funding line +$1,240,000 —
posts after final approval
posts after final approval
moves from 03/2027 to 09/2027
Queued
Primavera P6, District 5
activity 280000000
Letting 03/16/2027 → 09/14/2027
Letting 03/16/2027 → 09/14/2027
Needs Attention
Utilities
1 utility permit to recheck
Needs Attention
Phase Review
90% plans due date follows the new letting
Ready
EDMS
3 documents linked to the package
Needs Attention
Commitments
2 related commitments to recheck
Ready
Power BI semantic model
refreshed 06:00 AM
Write queue
| System | Operation | Status | Attempts | Last response | Correlation ID |
|---|---|---|---|---|---|
| Work Program | funding line | Pending (after approval) | 0 | — | wp-7f3a91 |
| Primavera P6 D5 | activity date | Queued | 0 | — | p6-2c18e0 |
| EDMS | link documents | Done | 1 | 200 OK 11/30/2026 10:28 AM | ed-90b4d2 |
| Power BI | refresh | Done | 1 | 06:00 AM | bi-11c7aa |
After final approval
- 1post funding line to Work Program
- 2send letting date to Primavera P6 District 5
- 3notify FYI recipients
- 4journal entry on the project
- 5nightly reporting extract
Work Program and Primavera P6 writes wait for final approval.
Every write is retried and logged.