ProjectSuite Change Management 1
Meera Kalyanaraman
Meera Kalyanaraman · Project Manager, District 5
Working as: Hector Valdivieso · until 12/18/2026
Prototype · example data

Change Request Package CR-2027-05-0142

Project: 446310-2-52-01 · SR 50 (Colonial Dr) from Kirkman Rd to John Young Pkwy — resurfacing and pedestrian lighting
District 5 · Orange County

Today: 12/08/2026

Project Information

FPID446310-2-52-01
Project NameSR 50 (Colonial Dr) from Kirkman Rd to John Young Pkwy — resurfacing and pedestrian lighting
District5
CountyOrange
Work MixResurfacing
Project ManagerMeera Kalyanaraman
Letting03/2027
Status:ActiveWork Program FY 2026/27–2030/31

Package Overview

Request DescriptionPedestrian lighting on 1.8 miles; letting moves from 03/2027 to 09/2027
Requested ByMeera Kalyanaraman
Created11/30/2026
Submitted12/01/2026
StatusIn Review
Current StepDistrict Estimates review

Impact Areas

Scope Summary

CurrentProposed
Work MixResurfacingResurfacing + Lighting

Funding

CurrentProposed
Phase52 Construction52 Construction
FY2027/282027/28
Amount$6,850,000$8,090,000 (+$1,240,000)
FundDDRDDR

Critical Schedule

CurrentProposed
Activity280000000 Letting280000000 Letting
Letting Date03/16/202709/14/2027

Project Info

CurrentProposed
New Location Work Mix—Lighting, MP 4.20–6.00

Comments / History

  • Rosalind Echeverri requested clarification: confirm lighting pole count·12/07/2026 2:14 PM

  • Meera Kalyanaraman replied: 58 poles, see estimate v2·12/07/2026 4:40 PM

  • System: reminder sent·12/08/2026 5:45 AM

Reviewer Route

Named workflow (Funding): D5 Funding Review — 2 steps
configured by the District 5 administrator
1. Scope Summary
Desmond Kittredge · District Design Engineer
Approved 12/02/2026
2. Funding
Order 1:Rosalind Echeverri · District Estimates
In review (2 days)
Order 2:Garrett Lindqvist · District Work Program Manager
Pending
3. Critical Schedule
Janelle Brooks · District Scheduling Engineer
Approved 12/03/2026
4. Central Office
Theodore Yanagisawa · Work Program Development
Pending
Work Program hold until 01/15/2027 — reminder e-mails at 05:45 (PSEE Send WPA Hold Reminder job)
Reminder sent to Meera Kalyanaraman · 12/07/2026 05:45 AM

Key System Update

What final approval will post to each system.

  • Work Program(via Work Program service)
    Phase 52 funding line +$1,240,000 —
    will post after final approval
    Pending
  • Primavera P6,
    District 5
    activity 280000000 Letting 03/16/2027 → 09/14/2027 — queued
    Queued
  • EDMS(eDOCS)
    Ready
  • Power BI semantic model
    refreshed 06:00 AM
    Ready
Preview notification e-mail