Packages and Work Program
Today: 12/08/2026
Open packages
184
Median days in review
6.5
On Work Program hold
23
Funding requested in review
$41.6M
Letting dates moved this quarter
17
Open packages by district
Median days in review by month
Packages by impact area
Slowest steps
Packages over 10 days in one step
| Package | District | Step | Days in step | Reviewer |
|---|---|---|---|---|
| CR-2027-05-0098 – SR 50 at CR 545 (Avalon Rd) — intersection improvements | D5 | District Estimates review | 14 | Rosalind Echeverri |
| CR-2027-05-0104 – SR 46 from Mellonville Ave to SR 415 — resurfacing | D5 | Work Program review | 13 | Garrett Lindqvist |
| CR-2027-05-0111 – SR 15/600 (US 17-92) from Shepard Rd to Lake Mary Blvd — safety improvements | D5 | Central Office review | 12 | Theodore Yanagisawa |
| CR-2027-05-0117 – SR 434 from SR 417 to Mitchell Hammock Rd — operational improvements | D5 | Scheduling review | 11 | Janelle Brooks |
| CR-2027-05-0123 – SR 500 (US 441) from SR 46 to SR 44 — resurfacing | D5 | Design review | 11 | Desmond Kittredge |